- GB Energy enters administration and receivership as $1 billion Victorian gas project stalls
GB Energy enters administration and receivership as $1 billion Victorian gas project stalls
McGrathNicol and FTI Consulting appointed after escalating costs and project delays derail funding for a major gas storage development intended to ease eastern Australia's looming supply shortages

GB Energy Holdings Pty Limited and GB Energy (VIC) Pty Ltd, the companies behind the approximately $1 billion Golden Beach Energy Project in Victoria, have entered voluntary administration and receivership after construction delays and rising costs left the development without sufficient funding to proceed.
Damien Pasfield and Matthew Hutton of McGrathNicol were appointed voluntary administrators of both companies on 6 November 2026, while Matthew O’Keefe and Chris Hill of FTI Consulting were appointed receivers and managers.
The appointments follow a deterioration in the financial position of the Golden Beach Energy Project, a proposed natural gas production and storage facility intended to address looming supply shortages in eastern Australia. The project had recently secured government approval to commence gas production in 2028, followed by storage operations in 2029.
Origin Energy, the project's contracted offtaker and a secured creditor, attributed the financial difficulties to delays in the development schedule and substantial cost increases that prevented the project companies from securing sufficient funding to reach a final investment decision.
Origin appointed FTI Consulting as receivers and managers, placing the project under the control of the receivers. Development activities have been suspended while the receivers assess the project's financial position and available options, including potential funding arrangements.
The Golden Beach Energy Project involves developing an offshore gas field near Victoria's Gippsland coast into a production and underground storage facility. Once operational, the project was expected to increase Victoria's gas storage capacity by approximately 70%, providing additional flexibility to meet seasonal and peak demand.
According to the developer, the facility was designed to deliver withdrawal capacity of up to 500 terajoules per day, representing more than half of Victoria's maximum daily gas demand during the financial year ended June 2026.
The insolvency appointments come at a critical point for Australia's east coast gas market, where regulators have warned of potential supply shortfalls toward the end of the decade. The Golden Beach project had been identified as a significant source of additional storage capacity, with its proposed commissioning timetable aligned with the period of anticipated supply constraints.
The receivers will now determine whether the development can be recapitalised or otherwise progressed, while the voluntary administrators assess the financial position of the two companies and report to creditors.